Hong Kong1979–2022A railway in layers
The MTR, in section
Hong Kong's metro was not built all at once. Each new line arrived in a city that already had railways, foundations and a harbour in the way, and had to pass over, under or around them.
Admiralty shows how. Its first two lines were planned together and share two levels. The two newest were dug in beneath them more than thirty years later, while trains kept running overhead.
- 1980Tsuen Wan LineLevels 2 and 3
- 1985Island LineSame levels, across the platform
- 2016South Island LineLevel 6 · −33.6 mPD
- 2022East Rail LineLevel 5
The film How the layers were laid down
A short animated film, from the first dig under Nathan Road in 1975 to the fourth railway tunnel under the harbour in 2022. It has no sound; the captions tell the story.
Loading…
Read the film as text
The network by year, and by level
Drag the year to see the network grow. Switch to Level to colour every station by how it was built: on a viaduct, at ground level, or underground. Select a station for its details.
Arrow keys move one year at a time. The station counts below update as the year changes.
- 98
- Stations open
- 46
- Underground
- 27
- Elevated
- 21
- At ground level
- 4
- Mixed levels
Scroll or swipe inside the map to see all of it.
Select a station on the map, or choose one from the list.
Lines are drawn in today's colours, also for years when they ran under another name. East Rail and the Tuen Ma Line's predecessors were built by the KCR and joined the MTR in 2007.
In three dimensions every line at its own level
The network in its real geography, with each line at its own level and depth stretched so the levels show. Turn it, tilt it below sea level, zoom in on an interchange, and follow the tubes under the harbour. Select a station to see how deep each line runs there.
Building the model…
Pinch, or hold Ctrl or ⌘ and scroll, to zoom
Highlight lines
Drag to turn · Shift-drag or right-drag to move · Pinch or Ctrl/⌘-scroll to zoom · With the model selected: arrows turn, Shift + arrows move, + and − zoom, 0 resets, Esc clears a station.Drag sideways to turn · Pinch to zoom · Use the buttons on the model to tilt. Tunnel dips and bridge heights are approximate.
Interchanges where the layers meet
Where lines cross, their platforms have to be stacked. Some were planned together, so passengers change trains by walking across the platform. Others were added decades apart, and the new platforms had to fit around the old ones.
How they built it six ways to make room for a railway
The level a line runs at depends a lot on how it was built. Building in a trench from the surface keeps a line shallow. Going through rock lets it go deep. Viaducts and bridges carry it above everything.
Sources and notes
Dates come from MTR Corporation and KCRC reports and government papers. Depths are harder to pin down: where no primary source gives a figure, the page says so.